Testing the CEPS
To test the CEPS, follow these steps.
G100434
Ground
230 V AC
Step Action
1 Use the shelf breakers to power off the module if the module’s
power is not already off.
2 Swap the CEPS with a new one.
3 Reboot the system to full service.
4 Return the faulty CEPS for service or replacement.
5 If the system fails to boot, go to “System fails to boot
completely” on page 16-24.