Seagate ST43401N/ND Guide d'installation Page 130

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 146
  • Table des matières
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 129
Parallel Migration Task List Example
122
2 Iteratively perform back-end regression testing.
3 Monitor and capture system dynamics (
sp_who, sp_lock, statistics
io
...).
4 Verify and document older system regression test.
Front-end simulation regression test suite
1 Iteratively do front-end simulation regression tests.
2 Monitor and capture system dynamics (
sp_who, sp_lock...).
3 Verify and document older system regression test.
Front-end Phase 1 and 2 regression test suite
1 Perform Phase 1 and 2 regression testing for local team.
2 Perform Phase 1 and 2 regression testing for users.
3 Monitor and capture dynamics (
sp_who, sp_lock...).
4 Make “go/no go” call for the shadow server.
5 Verify and document older system regression test.
6 Verify performance and functions on Server B.
Upgrade Server B (Shadow)
1 Alter sybsystemprocs.
2 Perform pre-upgrade verification.
3 Upgrade Server B to ASE 12.5.
4 Load ASE 12.5 environment from media dumps.
5Run
dbcc commands (checktable, checkalloc, checkcatalog).
6 Set baseline 12.5 configuration parameter values.
7 Perform dump of older databases from Server A.
8 Load dump into 12.5 system.
9Run
dbcc commands (checktable, checkalloc, checkcatalog) on ASE
12.5 databases. Be sure to verify the
dbcc log and error log.
Vue de la page 129
1 2 ... 125 126 127 128 129 130 131 132 133 134 135 ... 145 146

Commentaires sur ces manuels

Pas de commentaire